CN Completes $100 Million Memphis Yard Reconstruction

MEMPHIS, Tenn. — CN announced the completion of the $100 million multi-year construction project to reconfigure and modernize its Memphis rail classification yard.

“This project transformed an aged, inefficient rail yard into a state-of-the-art, effectively designed major terminal capable of handling existing and future traffic quickly and efficiently,” said CN executive vice-president Claude Mongeau, who will succeed retiring president and chief executive officer E. Hunter Harrison on Jan. 1, 2010. “Today’s yard can handle nearly double the traffic the old facility could in a 24 hour period.”

Memphis, a major freight distribution hub, is a key operating center on CN’s North American network. It is an important destination for freight traffic on the CN system, and the gateway to CN’s rail operations in the Gulf region. The city is also the largest U.S. location outside of Chicago where CN interchanges traffic with four of the major U.S. Class 1 railroads.

The new Memphis yard is CN’s second largest classification yard in the United States. It has a capacity of more than 3,100 freight cars with 45 tracks in the classification yard. It also has 12 receiving and departure tracks ranging in length from 5,000 to 10,000 feet. The revised operation can handle 35 or more freight trains per day.

It took more than two years to construct, effectively building a new rail yard on top of an existing one while never ceasing railroad operations. The configuration of the old Johnston Yard created operational challenges that at times affected CN’s ability to efficiently meet customer needs. The new yard removes those challenges, creating a terminal that optimizes our ability to move traffic in and through the yard.

“The old yard was removed section by section and rebuilt piece by piece,” said Keith Creel, CN’s executive vice-president, operations. “The yard now features the latest technological enhancements in railroad operations, including the newest switching technology to maintain safety and efficiency at all times.”

The yard reconstruction also included rebuilding of the terminal’s aged locomotive repair and car shops and upgrading of the locomotive fueling station.

Railfanning Review Podcast

Before you copy and paste this information to your website, please keep in mind this research took a lot of effort. Appreciate it. Learn from it. But do not plagiarize it. Yes, if you think we might be talking to you, we are.