Dallas Area Rapid Transit will advance segmented testing within the Silver Line Regional Rail’s central corridor for the first time later this month.
Residents and commuters in North Dallas, Addison, and Downtown Carrollton will soon see DART’s newest trains operating on newly installed tracks ahead of passenger service later this year. DART crews have recently finished installing and connecting more than 53 miles of new rail track along the project’s 26-mile corridor.
“We’ve made substantial progress installing and preparing the track, signals, and crossings to ensure we can test our vehicles in this central segment safely and efficiently,” Trey Walker, vice president of capital design and construction at DART, said in a release. “This is a major milestone and continues us on our path to have the Silver Line carrying passengers from Plano to DFW Airport and everywhere in between before year’s end.”
Testing will start the Week of April 27.
Segmented testing, which describes testing the train and operating systems on a specific segment of the project’s track alignment, is necessary as construction progress varies across the 26-mile rail corridor. DART began this process in the Fall of 2024, testing track infrastructure, signals, operating systems, and rail crossings between Plano and Richardson. Earlier this year, testing expanded to include the segment from DFW Airport to the current end of the constructed track near I-35 in Carrollton.
DART crews completed the connection of track between Downtown Carrollton and Dallas in mid-April, so vehicle testing can now progress through this area. Simulated train test runs, operating between Downtown Carrollton Station and the University of Texas at Dallas Station in Richardson, are expected to begin the week of April 27.
Silver Line trains will initially operate test runs on weekdays between 9 a.m. and 4 p.m., with activity gradually increasing as preparations continue for the start of service later this year. These runs are for testing purposes only no passengers will be permitted to board as trains make stops at Downtown Carrollton, Addison, Knoll Trail, and UTD stations.
Flaggers will be present, as needed, during the initial signal and crossing tests to guide drivers and ensure they cross the tracks safely.
Quiet Zones will be active once the Silver Line opens.
Once in service, the Silver Line will operate under a quiet zone ordinance along most of its 26-mile route. Train horns will only be used when necessary for safety, such as if something obstructs the tracks.
During segmented testing, trains must sound horns at all rail crossings to alert motorists and pedestrians. DART is actively working with each city along the corridor to submit federal Quiet Zone applications.
The Silver Line is more than 90% complete, with major construction expected to wrap up by the end of June. Later this summer, DART will begin running trains along the full route from Shiloh Road Station in Plano to DFW Airport Terminal B as all testing segments are integrated. Segmented testing is essential to confirm that each section of the track operates properly and that vehicles perform as intended.