Hochul Leans on Feds for Rising Costs of Gateway Tunnel

December 19, 2018---North Bergen--Governor Andrew M. Cuomo tours the North River Rail Tunnel that connects New Jersey and New York Wednesday night December 19, 2018. The North River Tunnels are a pair of tunnels that carry Amtrak and New Jersey Transit rail lines under the Hudson River between Weehawken, New Jersey and Pennsylvania Station in Manhattan, New York City. As of March 2018, up to $541 million for the Gateway Project, a program to build two additional rail tunnels under the Hudson River, was provided in the Consolidated Appropriations Act. (Kevin P. Coughlin/Office of Governor Andrew M. Cuomo)

(The Center Square) – Rather than try to downplay reports that costs for the Gateway Tunnel project are going up, New York Gov. Kathy Hochul leaned into it Tuesday.

Speaking at a press conference to unveil a new Penn Station concourse for the Long Island Rail Road, Hochul told reporters that it was important to get the word out regarding the increased cost of the passenger rail tunnels connecting New York and New Jersey under the Hudson River.

The current estimated cost is more than $16 billion, $2 billion more than what was estimated a year ago. The increase is due to inflation.

“We wanted to get those numbers out there early, so we can bolster our arguments to the federal government for a larger share,” Hochul said. “That’s exactly why it was important to get those numbers out now.”

The Gateway Tunnel project is considered to be a critical project not just for the two states but for the New England and Mid-Atlantic regions.

Currently, that corridor is served by pair of one-way tunnels that opened 112 years ago, connecting Penn Station to Weehawken, N.J. Amtrak and New Jersey Transit trains use the tunnels to shuttle thousands of rail passengers on a daily basis.

Besides shuttling commuters back and forth from the New Jersey suburbs, the tunnels are also a lynchpin for the Northeast Corridor, the busiest passenger rail system in the U.S.

A decade ago, flood damage caused by Superstorm Sandy heightened the need for new tunnels, leading officials from both states to lobby Washington for support.

Under the plan, two new tunnels would be developed, and once they are opened, work would begin on upgrading the existing tunnels to double the rail capacity.

In addition to the cost increase, media reports last week also indicated the project would not be completed until 2038, which is three years later than officials previously announced.

Two months ago, New York and New Jersey officials reached an agreement to split their share of the project, but the expectation is for the federal government to pay at least half, or more, of the cost.

The Gateway Project also includes replacing a 112-year-old bridge in New Jersey. The states have agreed to each pay $386.2 million for the Portal North Bridge. That’s expected to cover about 40% of the costs for that phase of the project.

Railfanning Review Podcast

Before you copy and paste this information to your website, please keep in mind this research took a lot of effort. Appreciate it. Learn from it. But do not plagiarize it. Yes, if you think we might be talking to you, we are.

About The Center Square 182 Articles
The Center Square was launched in May 2019 to fulfill the need for high-quality statehouse and statewide news across the United States. The focus of our work is state- and local-level government and economic reporting. A taxpayer sensibility distinguishes our work from other coverage of state and local issues.